Baan Suan Mok Construction

The Baan Suan Mok houses are built by TH-property's construction team, most of whom come from Prachuabkhirikhan town and live onsite at our projects in Hua Hin.



Foundations start with deep-set pad stones cast in reinforced concrete.




Then the floor beams are cast.




Then the floors are poured.




The pillars are cast and allowed to cure for 10 days.




Then the roof beams are cast and allowed to cure for a further 10 days.




Roof frames are of rolled steel profiles welded and rust-proofed.




Wallwork is done with 14cm cavity block, concrete rendered both sides and a gypsum skim on intenal walls for smoothness.




Conduits for electricity, water and air-con are embedded in the walls before rendering.




Our grey water soakaway systems are far superior and considerably more effective than elsewhere.




Ceilings are made of gypsum board suspended on a lightweight steel frame.




Our doors and windows as well as kitchen and bathroom furniture are made by our own team of carpenters.




Our woodwork finishings are simply beautiful.




And so is the finished property!